RTU First Start-up Sequence

  • Interactive decision labs
  • Built by working technicians
  • Path-based verifiable certificate
  • Exam preparation only
  • Worldwide online
Installation, Start-up & Commissioning
~14 min
intermediate

The call

New packaged RTU has been set on the curb. Electrical and duct connections are complete. You are called to perform first start-up and basic verification before handover.

Equipment
6-ton gas/electric packaged RTU, R-410A, economizer equipped, newly installed
Ambient
82°F
Site notes
Install crew reports power is on and thermostat is wired. No previous start-up has been performed. Condensate drain is connected.

Decision 1 of 4

The unit is set, wired and ducted. Nothing has been run yet and no readings exist.

What is the correct first action before energising the unit for start-up?