Read the drawings, plan the job, sequence the work, and hand over a pack another technician or inspector can follow — before tools hit the site.

8 modules 8 signature labsAcademy certificate (not a licence)

In development
HVAC Project & Install Planning Certificate (Academy)

What this certificate is — and is not

Academy issues a training certificate for planning competence only. This path does not replace EPA Section 608, NATE, SAQCC Gas registration, NITA/CDACC qualifications, trade licences, contractor licences, or local permits. Isolation, charging, and refrigerant handling still require the applicable statutory credential and qualified persons.

Why this path exists

Textbooks and campus notes lag the field. Inverter-driven equipment, A2L refrigerants, communicating controls and manufacturer sequences of operation change faster than print cycles do.

Path E trains drawing literacy, job planning, sequencing and handover on the systems technicians actually meet on site — so when the curriculum opens, the labs match the job in front of you, not last decade's chapter.

What you get is method: how a lead tech reads a set, plans a day, holds isolation discipline and hands over evidence another technician or inspector can use. The certificate covers planning competence only.

Where you study for the work you do

One diagnostic core, then local systems: the equipment, codes and manufacturer literature habits you will actually meet are layered on top by region.

Europe, Australia, Latin America and other markets use the same planning method — regional credential pages ship as those tracks open.

Start on a live HVAC track while Path E is in development

Enrol now in graded diagnostic labs with safety-fail marking — current recovery judgment, sequence-of-operation diagnosis and regional credential prep. Path E planning labs will sit on top of that same field standard.

  • Interactive decision labs
  • Built by working technicians
  • Path-based verifiable certificate
  • Know which exam to book
  • Worldwide online

Who this path is for

Working HVAC technicians and leads who can — or will — hold refrigerant credentials, but lose time on drawings, scope, sequencing and handover. This is not a “become an installer this week” path.

High-value diagnostic training we stand behind — work the graded labs, then book the credential that applies where you work: EPA 608, NATE, Red Seal, ARCtick, F-Gas, CDACC, SAQCC Gas or ESSCI.

Modules

The eight modules Path E is being built around. Titles and outcomes are published; lesson content is still being written to the same standard as the open paths.

  1. 01Drawing literacyPlans, elevations, schematics, legends and revision clouds on current split, RTU and VRF sets — read the set in the right order.
  2. 02Scope and constraintsWhat is in, what is out, plus access, occupied sites, tenant hours and the constraints that quietly reshape a day.
  3. 03Load and equipment at planning levelNameplate versus design intent on inverter and communicating kit — enough to plan the job, not full design engineering.
  4. 04Job plan and BOMTask list, materials, rentals and long-lead items — including line-set, control wiring and A2L-aware components — identified before mobilisation.
  5. 05Sequence of workDemo, set, pipe and wire, evacuate and charge, commission — an order that survives the manufacturer's start-up sheet.
  6. 06Isolation, permits and interfacesLOTO mindset, refrigerant handling boundaries, other trades on site and AHJ awareness built into the plan.
  7. 07Commissioning and evidence packReadings, photos, as-left condition and the manufacturer commissioning fields you actually fill, plus a sign-off structure that holds up later.
  8. 08Change orders and callbacksRecognise when scope shifts, and how bad sequencing and stale drawings manufacture callbacks.

Signature labs

Eight planning labs are scoped. Four of the eight briefs are workable now as practice: read the scenario, do the work on paper, then mark yourself against the same rubric a lead would use. These are not engine-graded and carry no certificate.

  • E-01 Drawing read
    Practice brief — rubric only

    A current split / RTU / VRF package set: mark the missing gas-line size, electrical, access and revision clouds a lead would refuse to assume.

    Work this brief now — scenario and self-marking rubric

    E-01 — Drawing read: what the set does not tell you

    Customer report: “Here is the set. Price it and start Monday — the consultant says everything you need is on the drawings.”

    • · Mixed package: one 7.5-ton RTU replacement plus a four-head VRF fit-out
    • · Mechanical sheets at two revisions, electrical sheet at a third
    • · No equipment schedule for the VRF branch controllers

    Your tasks

    1. 1. Put the sheets in reading order and record which revision governs.
    2. 2. List every item you would need before mobilising that the set does not state.
    3. 3. Mark the access and structural constraints that change the method.
    4. 4. Write the three questions you would send the consultant in writing.

    Scoring — 100 points, pass at 70

    • Revision control25 pts

      • · Identifies that sheets are at different revisions
      • · States which revision governs and why
      • · Refuses to price from superseded information
    • Missing information named specifically30 pts

      • · Branch controller locations and service access
      • · Line-set routes, lengths and lift
      • · Electrical supply capacity and disconnect locations
    • Constraints that change method25 pts

      • · Roof access, crane or hoist need, occupied-hours restrictions
      • · Structural support for the replacement unit
    • Written questions, not assumptions20 pts

      • · Questions are specific and answerable
      • · Nothing critical is assumed silently

    Automatic fail triggers

    • × Prices the job from a superseded revision without flagging it
    • × Assumes line-set length or electrical capacity rather than asking
    Trainer model answer (tap to reveal)
    1. Establish the governing revision on every discipline before reading anything else.
    2. Read plans, then sections, then schedules, then details — and list the schedule gaps.
    3. Record what is unknown as a question set, not as an allowance buried in the price.
    4. State the access and structural items that determine the sequence and the crew size.
  • E-02 Day plan
    Practice brief — rubric only

    Sequence a live occupied-site changeout — A2L or the regional equivalent flagged as awareness, not a licence: demo, set, pipe and wire, evacuate and charge, commission, in an order that survives the manufacturer's start-up sheet.

    Work this brief now — scenario and self-marking rubric

    E-02 — Day plan: an occupied-site changeout that actually finishes

    Customer report: “We trade from nine to six. The old unit has to go and the new one has to be running before we open the next morning.”

    • · Like-for-like packaged unit changeout on a trading retail site
    • · Crane slot booked for a fixed two-hour window
    • · Manufacturer start-up sheet must be completed on the day

    Your tasks

    1. 1. Write the sequence from arrival to sign-off with timings.
    2. 2. Mark the isolation and recovery points and who holds them.
    3. 3. Identify the two steps that will sink the day if they slip, and the fallback for each.
    4. 4. List the evidence you will capture as you go rather than at the end.

    Scoring — 100 points, pass at 70

    • Sequence integrity30 pts

      • · Demo, set, pipe and wire, evacuate, charge, commission in a workable order
      • · Crane window sits where the sequence can actually use it
    • Isolation and recovery placement25 pts

      • · Electrical isolation and proof-dead before disconnection
      • · Recovery completed by the qualified person before any cutting
    • Risk and fallback25 pts

      • · Names the two real critical-path risks
      • · Each has a specific fallback, not 'work later'
    • Evidence captured in-flight20 pts

      • · Photos and readings taken at the step, not reconstructed
      • · Start-up sheet fields planned in

    Automatic fail triggers

    • × Any cutting or hot work planned before recovery and isolation
    • × Plans occupied-hours work that puts the public inside the work area
    Trainer model answer (tap to reveal)
    1. Back-plan from the crane slot; everything that can be pre-staged is done before it opens.
    2. Isolate, prove dead, recover, then disconnect — never in a different order to save time.
    3. Pipe and wire before the evacuation window so the vacuum runs while other work continues.
    4. Capture readings and photos step by step so the start-up sheet is filled from evidence.
  • E-03 BOM and risk
    Practice brief — rubric only

    Incomplete drawings plus mixed-generation kit — communicating indoor, legacy outdoor: what you order, what you hold, and what you will not guess from a five-year-old typical.

    Work this brief now — scenario and self-marking rubric

    E-03 — BOM and risk on mixed-generation kit

    Customer report: “Match the existing. Just order what the last one used and we will sort the details on site.”

    • · Communicating indoor section proposed against a legacy outdoor unit
    • · Five-year-old typical detail with no equipment schedule
    • · Long-lead line-set and control components

    Your tasks

    1. 1. Split the bill of materials into order-now, hold-pending-confirmation and will-not-order.
    2. 2. State the compatibility question you must resolve before anything is ordered.
    3. 3. Identify the long-lead items and the date they must be committed.
    4. 4. Write what you will not guess and why.

    Scoring — 100 points, pass at 70

    • Compatibility named first30 pts

      • · Recognises communicating-to-legacy control mismatch as the governing question
      • · Refuses to order controls before it is resolved
    • BOM discipline25 pts

      • · Clear order / hold / refuse split
      • · Consumables and supports not forgotten
    • Long-lead handling25 pts

      • · Long-lead items identified with commit dates
      • · Programme impact stated
    • Explicit assumptions register20 pts

      • · Every assumption written down
      • · Nothing critical inherited from an old typical

    Automatic fail triggers

    • × Orders a communicating indoor section without confirming outdoor compatibility
    • × Copies quantities from an old typical without measuring the actual job
    Trainer model answer (tap to reveal)
    1. Resolve the control-generation question before a single control component is committed.
    2. Order what the measured job proves; hold what depends on the compatibility answer.
    3. Commit long-lead items only once the governing question is closed, and say what the delay costs.
    4. Publish the assumptions register with the BOM so nobody inherits a silent guess.
  • E-04 Handover pack
    Practice brief — rubric only

    Assemble evidence another technician or inspector can use: as-left readings, photos, sequence notes and the manufacturer commissioning fields you actually fill.

    Work this brief now — scenario and self-marking rubric

    E-04 — Handover pack another technician can actually use

    Customer report: “The client wants the O&M today. Just put the manuals in a folder and send it.”

    • · New split system plus controls integration, commissioned yesterday
    • · Readings taken on paper by two different technicians
    • · Drawings not yet redlined against the installed job

    Your tasks

    1. 1. List what the pack must contain to be usable by a technician who has never seen the site.
    2. 2. State how you handle a reading you cannot substantiate.
    3. 3. Redline policy: what gets marked as-built and by whom.
    4. 4. Write the outstanding-items list and who owns each item.

    Scoring — 100 points, pass at 70

    • Pack completeness30 pts

      • · As-left readings with units and where they were taken
      • · Photos of concealed work, sequence-of-operation notes, settings record
    • Evidence integrity25 pts

      • · Unsubstantiated readings are re-taken or marked outstanding
      • · No figure is transcribed from the drawing as though it were measured
    • As-built discipline25 pts

      • · Installed deviations redlined
      • · Named person responsible for the redline
    • Outstanding items with owners20 pts

      • · Every open item has an owner and a date
      • · Nothing hidden in a covering note

    Automatic fail triggers

    • × Signs off readings the technician did not take or cannot substantiate
    • × Issues a pack that presents drawing values as measured values
    Trainer model answer (tap to reveal)
    1. Build the pack for the stranger who will service this site in three years.
    2. Any number you cannot stand behind is re-measured or listed as outstanding.
    3. Redline the drawings against the installed job before the pack is issued.
    4. Close with an owned, dated outstanding-items list — not a disclaimer paragraph.
  • E-05 As-built reconciliation
    Coming with curriculum

    The installed job has drifted from the set — routes moved, equipment relocated, line-set length changed. Reconcile what is installed against what was drawn and state which commissioning values are now invalid.

  • E-06 Occupied-site access and staging
    Coming with curriculum

    Trading hours, shared lifts, tenant restrictions and a single loading bay: plan material staging, crew movement and protection so the work is possible without shutting the site down.

  • E-07 Mixed-generation controls interface
    Coming with curriculum

    Communicating equipment landing on an existing BAS: plan the point list, the sequence of operation you will actually be handed, and the commissioning steps that prove the interface — not just the mechanical plant.

  • E-08 Commissioning evidence review
    Coming with curriculum

    Review someone else's commissioning pack before handover: find the fields filled from drawings instead of measurement, the readings with no units, and the items nobody owns.

Planned certificate on completion: HVAC Project & Install Planning Certificate (Academy). Certificates are issued only for completed, live requirements — never for a curriculum still in development.

Available now: the free mechanical drawings guide

The first Path E skill is already published as a free field guide: sheet order, symbols, equipment schedules, job sequencing and the information most often missing from drawings. No account needed.

Train now on the open paths

Paths A–D are open with live graded labs, lessons, exam banks and Academy certificates.